Mirabel Aquatic Centre
Mirabel Aquatic Centre
Technical expertise behind a versatile sports facility
Delivered by Magil under a design-build contract for the City of Mirabel, the aquatic centre in the Saint-Augustin sector brings together competitive swimming, instruction and recreation in a facility of approximately 37 673 sq.ft.
The project drew on Magil’s expertise in design management, trade coordination and aquatic facility construction. From foundations and building systems to acoustics and stormwater management, delivery required close coordination across disciplines to meet the facility’s technical requirements and the needs of its users.
Technical Coordination | Meeting the Demands of an Aquatic Facility
Aquatic facility construction requires careful coordination of pools, specialized equipment, building systems and finishes. At Mirabel, Magil planned and supervised the work of specialist trades, managed quality control and coordinated commissioning. Humidity control was a key technical requirement. Ventilation and humidity control equipment also had to be integrated with the pool hall’s acoustic requirements. This work demonstrates Magil’s ability to coordinate facilities where building systems directly influence comfort and day-to-day operations.
- Structure and Envelope | Coordinating Long Spans and Multiple Materials
The building combines a steel frame with cross-laminated timber roof panels supported by steel trusses. This assembly accommodates the long spans required over the pools while allowing exposed wood to contribute to the interior character. Driven piles provide foundations suited to the site conditions. Construction also required close coordination at the interfaces between the structure, extensive glazing and exterior cladding. The envelope combines textured precast concrete panels with metal cladding.
- Acoustics | Improving Comfort in Busy Spaces
Acoustic requirements informed the use of wood-finished acoustic assemblies in the lobby and pool hall. These treatments help control reverberation and noise from aquatic activities and ventilation equipment. Magil coordinated the architectural and technical components to achieve the intended acoustic performance while preserving the design quality and material expression of the spaces.
- Value Engineering | Rethinking Stormwater Storage
One significant improvement involved the stormwater retention system beneath the parking lot. The team replaced the original plastic-component solution with a stone-and-geotextile assembly beneath permeable paving. The change reduced the cost and construction time for this work. It provides a practical example of Magil’s approach to value engineering: reviewing alternatives with project partners and selecting solutions that respond to the project’s specific constraints.
Collaboration | Bringing Design and Construction Together
Through the design-build model, Magil managed consultant coordination and streamlined design management for the City. Civil and building services trade contractors participated in meetings with the design consultants, bringing practical construction knowledge into technical discussions. This collaboration supported the evaluation of alternatives, coordination between disciplines and construction planning through commissioning. It also helped the team manage pandemic-related procurement constraints affecting steel, wood and ventilation equipment.
- A Community Resource
Located near École secondaire du Maréchal, the centre serves families, school groups, sports clubs and athletes. Its complementary pools accommodate swimming lessons, training, competition and recreational activities. The bright lobby, spectator seating and multipurpose rooms extend its role beyond swimming. The project demonstrates Magil’s ability to deliver technically demanding sports facilities that also provide welcoming places for people to gather and connect.